PE gas pipe is a more popular and widely used gas pipeline, and it plays an increasingly important role in daily engineering construction. However, if the details of the PE gas pipeline construction are not done well, it will affect the subsequent use effect. Service life, so today I will talk about the issues that should be paid attention to during construction.
Trench: trench excavation requires a good slope control. If over-excavation or soil replacement, the soil must be tamped to prevent the sinking of the pipe from causing water on the reverse slope. The trench can be lowered only after the leveling measurement meets the design requirements.
PE gas pipe connection: the connection adopts hot melt connection and electrofusion connection:
(1) Hot-melt connection: Before and after the hot-melt connection, the dirt on the two heating surfaces of the heating plate of the connecting tool should be wiped with clean gauze to prevent affecting the thermal efficiency and joint quality. The heating time, heating temperature, holding pressure, and cooling time during connection should comply with the regulations of the pipe and pipe fitting manufacturers. During the holding and cooling period, no movement or external force shall be applied, otherwise the joints that have not yet reached a higher compressive strength will not be formed. The uniform flange affects the uniform compression of the joint. Both ends of the butt joint should be pin milled to ensure a good vertical joint between the two ends to ensure a good edge. Otherwise, the contact area is reduced and the strength is weakened.
(2) Electrofusion connection: When connecting by electrofusion, ensure that the electrofusion tool is connected correctly, and the setting of the energizing current and energizing time should meet the requirements of electrofusion accessories. The electrofusion socket surface is required to be clean, and the two ends of the pin milling should be connected vertically. Use a knife to scrape off the oxide layer on the electrofusion surface and roughen the electrofusion surface to increase the contact surface. Before the pipe is inserted, it is necessary to mark the insertion length position, to ensure sufficient length, to ensure the area of the electrofusion connection, and to enhance the quality of the connection joint. The saddle-shaped electrofusion connection also needs to clean the surface, and it is required to tighten the pipe flat and fix the screws to make the contact surface coincide.
Backfilling: The strength and rigidity of gas PE pipes are not as high as those of steel pipes. There should be no sharp objects such as bricks and stones around the pipes. However, there are many sharp objects in the underground of the old city reconstruction. Therefore, sand should be laid before the pipes are down. A layer of sand to ensure the safety of the pipeline.
Working with air: For PE pipes above De110 connected to straight pipes or tee connections, you can select special fixtures for PE pipes according to the air source conditions (single and double air sources), and then connect with electric fuse sleeves after cutting off the air source.
If the end of the pipe is plugged with a flange head, the flange head can be used to connect the pipe without stopping the air. When opening branch pipes smaller than De63 on PE pipes above De110, use electric fusion saddle tee without stopping the gas. After the saddle tee is installed on the pipe, use a cutter to open the original pipe for ventilation.